NioCorp's whole plan for its Elk Creek mine in Nebraska leans on one lender: the Export-Import Bank of the United States. That lender's legal authority to approve new deals runs out on 31 December, unless Congress renews it.
That is why the NB board has spent the past week reading defence bills instead of drill results.
How much NioCorp needs
The updated feasibility work released in August put Elk Creek's upfront cost at about $1.849 billion, roughly $708 million more than the previous estimate.
The stock traded at $2.55 on Wednesday afternoon, up 1.3% on the day.
Management plans to cover about 65% of that with debt and the rest with equity. In October, EXIM signed a letter of support saying it still targets debt financing equal to about 65% of upfront costs, and that it will move its due diligence toward review "as expeditiously as practicable".
A letter of support is not a loan. The quarterly report lists NioCorp's ability to get a final commitment from EXIM as a risk.
The deadline
Congress last renewed EXIM in December 2019, for seven years. That charter expires on 31 December 2026. If it lapses, the bank can manage what it already has on its books but cannot approve new transactions.
This has happened before. In 2015 the charter lapsed for five months.
The likely fix is the annual defence bill. The Senate's version included a short-term EXIM extension at committee stage, and the House and Senate were still reconciling their versions in October. Until a final bill passes, the extension is not law.
What NioCorp has in hand
NioCorp ended September with $403,364 in cash, though management says it has the resources to meet obligations due within a year. In October it signed a binding take-or-pay agreement with Traxys for half of the mine's planned ferroniobium output. The other half stays with ThyssenKrupp.
Customers, then, are lined up. The money to build is not.
If Congress renews EXIM before New Year, the Elk Creek loan stays on track. If it does not, NioCorp's biggest financing piece waits on Washington.